ITANAGAR, Oct 7:
Electricity supply from Ranganadi Hydro Electric Project to Upper Subansiri, West Siang, Siang, East Siang, Lower Dibang Valley, Lohit and Namsai will be disrupted from 9 a.m. to 5 p.m in two phases from October 12-16 and from 21-25 next.
This will be due to shifting of 132 KV Ziro-Roing via Daporijo, Aalo and Pasighat Transmission Line at some locations to make way for construction of Potin to Panging Trans-Arunachal Highway and for other annual maintenance works on the line.
The supply however will be normalized every evening before dark, said executive engineer, SLDC and transmission division-ii, Itanagar in an official release.